December 27, 2012
I-77 pipeline will restart, but agency has list of demands
Page 2 of 2
Advertiser

Sigman said the Pipeline and Hazardous Materials Safety Administration approved replacing the portion of the pipeline that exploded -- instead of the entire pipeline -- because "if they replaced an all-new pipe, there would be all new standards and this letter would not be necessary."

The pipeline safety agency proposed that NiSource partially test the pipeline and its valves to ensure its safety. But Sigman said he prefer that they are fully tested.

"Partially tested only verifies it partially," he said. "We are not a regulator, we cannot tell [the gas company] what they can and cannot do but we want to make sure they understand our concerns and explain how to make it safe. We want to make sure we're all on the same page and feel like it's the safe thing to do."

Also, Sigman questions why the agency told the gas company that it would allow the pipeline pressure to be at 80 percent, which would enable it to sustain pressure of 741 pounds per square inch.

When the pipeline exploded, the pipe was 70 percent thinner than it should have been, but still should have been able to sustain pressure of 921 pounds per square inch.

"One question we have is, 'How did they determine that number? Is that just an arbitrary number?'" Sigman said. "We think they need to do some other things before they put some more pressure on it."

Sigman said he'd like to see scientific engineering studies performed to "make sure the blast is not happening somewhere else."

Kanawha County Commission President Kent Carper said that since a portion of pipeline was so deteriorated before it exploded, it should be confirmed that the rest of the pipeline isn't as dangerous.

"The community has an absolute right to be safe. The traveling public driving over interstates have a right to be safe and the first responders deserve better than this," Carper said. "It's incumbent on the gas company to prove to the regulatory authorities that the line is intact from beginning to end."

Chevalier Mayes, a communications manager for NiSource, did not return phone calls Thursday.

CORRECTION: An earlier version of this story originally said the state Public Service Commission was the agency that gave approval to restart the pipeline. The PSC is only allowed to provide comments and input regarding the federal Pipeline and Hazardous Materials Safety Administration order, a PSC spokeswoman said.

Reach Megan Workman at megan.work...@wvgazette.com or 304-348-5113.

Recommended Stories

Copyright 2012 . All rights reserved. This material may not be published, broadcast, rewritten or redistributed.
Popular Videos
The Gazette now offers Facebook Comments on its stories. You must be logged into your Facebook account to add comments. If you do not want your comment to post to your personal page, uncheck the box below the comment. Comments deemed offensive by the moderators will be removed, and commenters who persist may be banned from commenting on the site.
Advertisement - Your ad here
Get Daily Headlines by E-Mail
Sign up for the latest news delivered to your inbox each morning.
Advertisement - Your ad here
News Videos
Advertisement - Your ad here
Advertisement - Your ad here